Hi All: Highlights for this week include:
1. Client is experiencing difficulties downloading wireframe submissions. Topcoder to come up with an alternate methodology to facilitate viewing
2. Client to use the milestone feature in Topcoder’s Direct application to enter key milestones for producing assets and documents for required elements
3. Topcoder to show client how to view bug race progress in Direct
4. Alternate strategies to be pursued in addition to smart cloud set-up
For the full report, see below. If there are questions or concerns, please let us know.
Thanks
Sarah
Project Status Report
| Project Name: | Prepared by: | Period Ending: |
| Medicaid Provider Screening Portal | Sarah Ramkissoon/Andy LaMora | 18-Oct-12 |
Executive Summary
| Item | Comments |
| Overall |
|
| Scope/Quality |
|
| Schedule |
|
| Budget/Resources |
|
| Contest Management |
|
upcoming Milestones/Deliverables Summary
| Project Milestones/Deliverables |
Estimated End |
Revised End |
Status |
Reference |
| Complete Workflow for All Providers |
Late-Oct |
Risk |
r1, i2 |
|
| Administrative Workflow |
Mid-Oct |
Stable |
r1,i2 |
|
| UI wireframes (all) |
Late-Oct |
Stable |
r1 |
|
| Prototype |
November |
Risk |
r1 |
|
| Bugs |
Ongoing |
Stable |
Upcoming Activities
| Work Required - Sponsor |
Oct 22 – Nov 2:
Nov 3 – Nov 9:
|
| Work Required – Topcoder |
Oct 22 – Nov 2:
|
ISSUES and RISKs Summary
Ref # |
Description |
Reported Date |
Action By Date |
Status |
|
i5 |
Issue: Client is experiencing difficulty downloading UI submissions, in particular wireframes due to their size.Action: Topcoder will propose a new methodology to facilitate wireframe download and viewing |
10-18-12 |
10-25-12 |
Open |
|
r5 |
Risk:IBM License test requires time to conduct test and review results. If the results are not as expected, a new/alternate strategy/discussions may be requiredAction: Expedite testing by using an IBM copilot to set up smart clouds, enabling POC testing on the IBM stack.
Update: Issue is still unresolved – alternate strategies will be explored in addition to pursuing smart cloud set-up |
09-20-12 |
10-21-12 |
Open |
|
i3 |
Issue: Client is concerned that feedback to UI wireframes are not being reflected and client is having trouble tracking which wireframes reflect feedback given by Angie.Action: Topcoder is running short bug races to make wireframe changes.
Update: Andy to show Dan how to follow bug races in Cockpit. Topcoder’s James will update the demo box twice weekly with wireframe updates (on a scheduled basis where possible) |
09-26-12 |
10-21-12 |
Open |
|
r1 |
Risk: A significant number of new provider organizations have been provided by client in mid-late September timeframe. As a result the time to complete the UI wireframes that included these new organizational types has increased.Action: Run the required organizational wireframes contests as aggressively as possible, including in parallel where possible, or with very short periods between contests where parallel is not possible. |
09-20-12 |
10-21-12 |
Open |
|
i4 |
Issue:Death master file access: will not be available. For development purposes, it will be assumed that a file will be uploaded weekly or monthly and a webservice utilized to process the file. A simple screen interface will be created to facilitate the upload. |
10-11-12 |
10-15-12 |
CLosed |
|
r3 |
Risk: Topcoder is currently experiencing technical difficulties with the software that allows for downloading of judging bundle packages. Action:Topcoder staff are working on getting the issue resovled with highest priority.Update: Judging bundles are now available for download |
09-20-12 |
10-03-12 |
Closed |
|
i2 |
Issue: Strategy to address licensing for IBM assets requiredAction: Feedback on the elements to port provided by client. Creation on contest to port elements to IBM stack in progress | 07-26-12 |
08-31-12 |
Closed |
|
r2 |
Issue: Developers require API access to 3rdsites to check for licensing and other authorization information Update (Aug 16, 2012): MN DHS and CMS (state and federal health agencies respectively) are looking into getting API access.
Alternate: Create well-formatted private web pages that allows for screen-scraping, and query with querystring tokens, post, etc |
07-26-12 |
08-23-12 |
Closed |
|
i1 |
Issue: Strategy required on IBM stack vs. generic stackResolution: Build two POCs ( “hello world” applications) and implement open source stack version. Client will then prioritize elements to port to the IBM stack |
07-12-12 |
07-31-12 |
Closed |
Project budget update
|
Ref # |
Description |
Comments |
|
1 |
- Estimated forecast for Oct – Nov: $170,000 |
n/a |
|
2 |
Actual contest cost to date: $325,000 |
Budget on Track as Expected |
Completed Activities
| Completed Activities (Sept 21 - Oct 7) |
|
-